CASE STUDY
St Josephs Catholic School
EMH Services was tasked with renovating the main commercial kitchen and overseeing the entire M&E design and installation within a tight summer break schedule.
Location:
St Josephs Catholic School, Salisbury
Duration:
2 Months
Trades:
EMH Electrical, Mechanical contractors, Plumbers, HVAC engineers, Lagging company, M&E designers & IT company
Clients need:
Renovation of the main commercial kitchen required an M&E contractor to handle the project from M&E design through delivery within the summer break.
Solution:
EMH Services will provide M&E consultancy work to rectify the kitchen's design and infrastructure in collaboration with the catering contractor. They will supply electrical, plumbing, heating, HVAC, and ventilation installation services. EMH will stay in nearby accommodation to work longer hours and ensure the project's timely completion.
Scope of works
Enabling works – install site power/temporary lighting
Electrical – Isolations and strip-outs
M&E design and consultancy
Containment works for all services.
Electrical installation works: New 3 phase 250A submain and Schneider Distribution Board, Small Power, Kitchen power requirements, Mechanical power requirements, Supply and fit of Lighting, Lighting Control cabling, Fire Alarm, Data cabling, and security wiring.
Plumbing works – Domestic water supplies and above-ground drainage
Heating Engineers – Alterations to the existing space heating pipework
Lagging – Commercial pipe lagging services due to existing asbestos lagging being removed
HVAC services – To install a new heating and cooling system in both the kitchen and school dining room
Ventilation – Supplies for AHU to kitchen and ventilation for WC’s and store room
To work out of hours evenings and weekends so as not to disrupt F&P
Test and commission system
Proposed Electrical Services Lighting layout (Click to enlarge)
Proposed Electrical Services Small Power Layout (Click to enlarge)
Proposed Mechanical Services Layout
(Click to enlarge)